F Block Extension Project

We are very pleased to confirm that work has now started on our classroom extension project. Building contractors will be on site until the summer working on the new car park area, the four classroom extension to F Block and the removal of the old mobile classrooms. The new classrooms are planned to be ready for the start of the new school year in September 2018.

Northwest 2

A few photos showing the areas concerned before work begins are in the attached gallery further down this page, this page will be updated as the project progresses.

22-3-18

Work has now begun, the mobiles have been demolished and removed from site, work has begun on laying the new Car Park area.

17-4-18

The ground has been cleared and footings excavated. The extended parking area is now in use and repairs have been made to the side access road.

19-6-18

Work has progressed nicely despite a couple of issues, the brickwork is now complete and roof trusses are being installed.

10-7-18

Work is still progressing with the roof nearly complete.

Snapshot - 13 - Rear Dome - 2018-07-10 14-11-06

F Block extension

24-8-18 

New extension completed and handed over to Campion School ready for the start of the autumn term
 
FBlockOutside